Wednesday, August 27, 2014

TIMELINE..........

01.07.2013 - 1st started looking for land in Avoca/Copacabana
18.08.2013 - Found land
10.09.2013 - Sale agreed
17.12.2013 - Build plans finalised
20.12.2013 - Submitted to council and RFS
08.01.2014 - Plans submitted to BASIX
19.03.2014 - DA approved
15.04.2014 - Finance approved
14.05.2014 - Build commenced
30.06.2014 - Tile and electrical appointment
28.04.2014 - Slab down
12.07.2014 - Lower frame commenced
23.08.2014 - Upper level commenced
18.09.2014 - Brickwork completed
24.09.2014 - Roof Timbers completed
10.10.2014 - Roofing fireproofing completed
13-17.10.2014 - colorbond roofing
20.10.2014 - gutters, fascias and eaves commenced
24.10.2014 - A/C installation commenced
07.11.2014 - All cladding installed
18.11.2014 - Plumbing and electrical rough in
29.11.2014 - All walls and ceilings plasterboard installed
12.12.2014 - Kitchen units installed
15.12.2014 - internal doors, skirting and architraves  installed
19.12.2014 - Bathroom cabinets and bath installed
5.01.2015 - Tiler started